August 14, 2009
Progression
The new sanctuary building is progressing nicely.
The underground utilities have been run, the foundation is in, the structural steel frame is complete, and the roof system is installed. Expect to see the metal studs for all the interior and exterior walls to be completed over the next several weeks. Then the next step will be to “dry-in” the building which includes all the exterior masonry, as well as the exterior doors and windows. It is very exciting to see so much progress.
Posted by Warren Brown at 5:16 p.m.